"We have shifted the date for contractors to bid on Phase 3 of the SR 44 widening project to May 2027. Extra time is required to acquire all right of way needed for the project." The Georgia Department of Transportation posted that on Facebook, and The Eatonton Messenger quoted it in September. Phase 3 is the section that runs between Harmony Road/Phoenix Road and Carey Station Road. That includes the Putnam County stretch of Lake Oconee Parkway where Harmony Crossing sits.
The same article reported a second change on that stretch. A new traffic signal at the Harmony Crossing entrance was scheduled to go live September 22. It faces the entrance to the new Publix site on the east side of SR 44 and the Harmony Crossing plaza on the west. Taken together, the two items explain this end of the Parkway. The places to stop are filling in on both sides of the road now. The widened road and roundabout planned for this intersection are still years away, so a signal will hold the spot until they're built.
Why the Signal Came Before the Widening
According to the Messenger, the department ran a traffic study and found that both SR 44 and the side roads met the volume thresholds for a signal. Without one, drivers on the side roads would have faced large delays, including drivers leaving Harmony Crossing and the new shopping center. The first activation date slipped by about a week. Will Volk, GDOT's District 2 Communications Officer, said crews needed more time to put down permanent striping before the signal went live.
The signal is temporary by design. The Messenger's caption says it "will give way to a roundabout when the widening project reaches its conclusion." The roundabout has been on the plans for a while. In 2023, Lake Oconee News placed it at the Harmony Crossing entrance, about a quarter mile north of the Harmony Road/Phoenix Road intersection. GDOT's SR 44 project hub lists it as the Harmony Plaza/Lake Country Village roundabout. The hub names a second Putnam County roundabout at Scott Road/Lake Pointe Drive. In Greene County it lists roundabouts at Merchant Street, Linger Longer Road/Westend Park, Carriage Lane/Airabella Boulevard, Carey Station Road and the Richland Connector.
So the traffic at Harmony Crossing reached signal-level volume before the shopping center across the road had even opened. The anchor tenant on the other side is the next reason to turn in.
What Is Going Up on the East Side
The Publix in the Lake Country Village/Towne Center development has no announced grand-opening date. Publix held a walk-in hiring event for the store on September 11 and 12 at its existing Lake Oconee Village location. The Messenger's sources pointed to a possible mid-November opening, but Publix hasn't confirmed it. As of this Thursday, that would be a few weeks away, and it's still only an estimate.
Publix is meant to be the first piece of a bigger project. The developer's plan calls for multi-tenant retail, outparcels, a hotel and a conference center on the property. The overall project address is 1024 Lake Oconee Parkway. When the Messenger covered the plan in December 2024, it described retail and dining, residential space, and a hotel and conference center. It reported the groundbreaking in July 2025. No other business has been named as a signed tenant. For now, the east side of the signal is a grocery store with room around it for more.
What Is Already Open Along This Stretch
The newer businesses on this end of the Parkway didn't wait for the Publix. Lake Oconee Life's October 14 roundup lists several that opened this year along this end of the Parkway.
- Tee Time 44, 1027 Georgia 44, Suite 400, Eatonton. Bryan and Amy Pulliam held the ribbon-cutting September 10. The space has indoor golf simulators, lessons and club fitting, plus a restaurant and bar. Brett and Julie Riccardi run the food and beverage side, according to The Eatonton Messenger. Lake Oconee Life notes that the simulators are Full Swing systems and that you can go for dinner and drinks without playing a round.
- Brilliance by Design, 1023 Lake Oconee Parkway, Eatonton. It opened August 10. Owner Tonya Miller is a local builder and interior designer, and she opened the shop after clients kept asking where to buy the pieces from her projects. It stocks home goods and hostess, birthday and thank-you gifts. Lake Oconee Life says its cocktail mixes have become a shop favorite, and the store has a mascot named Rowdy.
- InMotion Wellness Studio, 1124 Lake Oconee Parkway, Suite 130, Eatonton. Lake Oconee locals Pablo and Dana Santamaria offer assisted stretching. Each client starts with a Movement Score assessment that uses motion capture imaging, and the first session is a free demo.
- Oconee Bagel Co., at the Lake Oconee Farmers Market in Harmony Park at Harmony Crossing. The bagels debuted at the market in May 2026. They're hand-rolled, then boiled and baked. Lake Oconee Life says the stand is there most Saturdays from 8 a.m. to noon, by the fountain on the corner, and recommends the everything bagel. Check the market's current schedule before a Saturday trip this late in the year.
The list has a range. Tee Time 44 covers a rainy afternoon or a winter evening. Brilliance by Design is a stop for a hostess gift on the way to dinner. InMotion is a standing appointment. The bagel stand is a Saturday-morning stop. All four give people a reason to turn off the Parkway, and none of them is the grocery store.
The Road Schedule, Phase by Phase
The widening is moving from south to north, and the Harmony Crossing section comes last. GDOT's GeoPI project pages show where things stand:
- Phase I, Greene County, from south of King Drive to north of Town Creek Boulevard. Under construction. The GeoPI dashboard shows it 23.25 percent complete, with a current completion date of November 29, 2028.
- Phase II, Greene County, from Carey Station Road to south of King Drive. Under construction. The GeoPI dashboard shows it 8.59 percent complete, with a current completion date of August 31, 2030.
- Phase III, from Harmony Road/Phoenix Road to Carey Station Road. Contractor bidding has moved to May 2027 while GDOT finishes buying right of way. The earlier deadline for property owners to sign right-of-way agreements was September 1. The Messenger reported that GDOT's plans have Phase III construction starting in 2027.
The dashboard figures are a live snapshot, so both the percentages and the dates can change. Even so, they show that the Greene County construction zones south of here have completion dates in 2028 and 2030, while the Harmony Crossing section hasn't gone to bid.
Running Errands Here Between Now and the Roundabout
For the next few years, this end of the Parkway will run on a signal designed as a stopgap. GDOT's study found the side roads already busy enough to need it, and that was before a grocery store opened on the east side. The signal will also carry the grocery traffic once Publix announces and reaches its opening date.
Lake Country Village's longer plan for retail, outparcels, a hotel and a conference center would add more traffic to the same entrance. The roundabout meant to replace the signal depends on the Phase III bid in May 2027 and on the right-of-way purchases that pushed the bid back. Phase III construction is planned to start in 2027, after that bid.
We follow changes along Lake Oconee Parkway the way our neighbors do, one new business and one detour at a time. If you'd like an update when the Lake Country Village Publix sets its date, or you want to know how the SR 44 schedule affects the drive to your part of the lake, Jennifer Vaughan and our team are glad to help from our market center in Village Park. Love Where You Live, and let's get started.